We recently completed our drill and blast scopes of work at Rio Tinto’s Mesa H, B and C projects, located in the Pilbara.
Both projects were completed with an exceptional safety record and some impressive productivity achievements
MESA H – DRILL & BLAST CONTRACT
- Mobilised October 2020
- Demobilised May 2021
- TRIFR & LTIFR 0.00
- Drill rig availability 94%
- Successful complex blasting in close proximity to infrastructure and the development of a blast design, execution and evaluation methodology
- Awarded the Rio Tinto Golden Quoll award for environmental excellence in partnership with Georgiou, Benchmark Surveys and Emeco Group
- Winners of the Rev Cup Challenge!
MESA B & C – DRILL & BLAST CONTRACT
- Mobilised March 2020
- Demobilised April 2021
- TRIFR & LTIFR 0.00
- Blasted circa 1,305,000 bcm
- Productivity 10.3% above tender
- Drill rig availability 94.4%